Photovoltaic Cable Tray: Specifying Ventilated Tray for Solar Plants
Why PV plants need their own tray rules
Photovoltaic plants route large quantities of DC cable between strings, combiner boxes and inverters — usually on perforated tray that protects the cable while letting heat escape. For ground-mounted, distributed and rooftop plants, the standard choice is a ventilated perforated tray in galvanized or zinc-aluminum-magnesium steel, with single-side zinc coating up to 275 g/m² (about 19-20 um) for long outdoor service. Three things separate a PV run from indoor cable management: cable that never cools down, sections that run for kilometres without a support, and finishes that are exposed to rain, dust and ultraviolet for the life of the plant.
See the full size and specification comparison table
Which sections PV cable actually needs
Common sections are 50x50, 100x50, 100x100, 150x100, 200x100 and 200x150 mm, with 300x100 and 400x200 available on request. Brackets are fixed with expansion bolts at 1.5-3 m spacing depending on section and load. Section size follows the cable: 50x50 and 100x50 for string runs, 100x100 to 200x150 for combiner-to-inverter feeders, and 300x100 or 400x200 where several inverters are gathered into one collection line.
Why the fill ratio is stricter in the sun
Because DC cable ampacity drops as ambient temperature rises, the fill ratio rule is stricter than indoor work: national standard limits are 40% for DC solar cable, and in high-temperature environments we recommend no more than 30% with a further 20% margin reserved for future string additions. A tray sized for a cool indoor corridor will overheat in a desert plant if the fill ratio is copied across without the derating.
Which finishes survive outdoor service
Material selection follows the site atmosphere: hot-dip galvanized steel for normal inland plants, zinc-aluminum-magnesium for high-humidity or coastal sites, and 201/304/316 stainless where fertilizer or chemical plants surround the array. Grounding is part of the tray specification, not an afterthought — copper grounding bolts should be ordered as standard accessories with every run.
Section-by-section selection for a PV route
The table below maps the four typical segments of a DC route to a section, a sheet thickness and a bracket spacing, so the same decisions can be made per circuit before the quotation is issued. Thickness follows the same rule as indoor tray — it increases with width — and the spacing stays inside the 1.5-3 m range set by the section size and the load.
What we return with the quotation
When you send us your string layout and cable schedule, we return a section-by-section bill: tray size, finish, bracket spacing, fitting counts and a fill-ratio check for every run. That quote is the fastest way to avoid the two most common PV tray mistakes — undersized sections that overheat, and finishes that rust out in year three.
| Route segment | Suggested section | Sheet thickness | Bracket spacing | Fill ratio |
|---|---|---|---|---|
| String to combiner box | 50 × 50 / 100 × 50 mm | 1.0 mm | 1.5–2 m | 30% recommended (40% standard limit) |
| Combiner box to inverter | 100 × 100 / 150 × 100 mm | 1.0–1.2 mm | 1.5–2 m | 30% recommended, 20% reserved for later strings |
| Inverter to DC trunk line | 200 × 100 / 200 × 150 mm | 1.2–1.5 mm | 1.5–2 m | 30% recommended (40% standard limit) |
| Collection line, large cross-section | 300 × 100 / 400 × 200 mm (made to order) | 1.5 mm and above | 1.5–3 m | 30% recommended (40% standard limit) |
Products related to this article

Perforated Cable Tray
Perforated cable tray with ventilated bottom, width 50–600 mm, galvanized or powder coated
View product →
Color Steel Cable Tray
Pre-painted color steel cable tray, mill-baked finish, RAL colors, width 50–600 mm. Clean
View product →
Channel Cable Tray (Solid Bottom)
Solid bottom channel cable tray: galvanized steel, stainless and aluminum, width 50–600 mm
View product →