Cable Fill Ratio and Support Span: The Two Numbers Behind Every Tray Order
What fill ratio actually means
Cable fill ratio is the percentage of the tray cross-sectional area occupied by cable. For power and control cable in trough or perforated tray, most national standards cap fill at 40% for the cable's own heat dissipation; data and fiber cables in ventilated mesh tolerate higher figures because the open structure lets heat escape. For photovoltaic DC cable the limit is 40% by standard and 30% is best practice in hot climates, keeping another 20% in reserve for later expansion.
See the full size and specification comparison table
What support span actually means
Support span is the distance between hangers or brackets. Published load ratings assume 1.5 m or 2 m spans; at 3 m the allowable load falls sharply because deflection grows with the cube of the span. The tray depth, sheet thickness and steel grade must all match the span on your drawings — a 2 m-rated tray hung at 3 m will sag past its deflection limit long before any load table is consulted.
How the two numbers interact
The two parameters interact: deeper tray sections (100-200 mm) carry more cable at the same fill ratio and tolerate longer spans, but cost more per metre. The economical route is usually a deeper section on the standard 1.5-2 m span rather than a shallow section forced onto custom close-spaced supports.
How the deflection curve behaves
Because deflection grows with the cube of the span, moving the same section from a 1.5 m spacing to 3 m multiplies deflection by roughly eight, while the allowable load falls sharply. The three spans in the table below are therefore not interchangeable: they are three different structural conditions, and only the spacing shown on the drawing is valid for the load calculation.
What to send so both numbers can be checked
Send us your cable schedule — cable types, outer diameters, quantities per run and the structural support spacing on your drawings — and our engineers will return a fill-ratio check and a load calculation with the quotation, so the section you order passes site inspection the first time.
| Support span | Relative deflection (1.5 m = 1.0) | Allowable load | What to do |
|---|---|---|---|
| 1.5 m | 1.0 × | Published rating applies | Standard choice for most installations |
| 2.0 m | ≈ 2.4 × (2 / 1.5)³ | Published rating applies, smaller margin | Use when the drawing calls for 2 m; keep the thickness listed for that width |
| 3.0 m | ≈ 8.0 × (3 / 1.5)³ | Falls sharply — not a catalogue figure | Ask for the tested deflection data, move to ladder type, or add intermediate supports |
| 4.0 m and above | ≈ 19 × (4 / 1.5)³ | Outside the usual published curves | Not recommended without a project-specific calculation |
Products related to this article

Ladder Cable Tray
Hot-dip galvanized ladder cable tray, width 100–600 mm, rung spacing 250/300 mm, NEMA VE 1
View product →
Channel Cable Tray (Solid Bottom)
Solid bottom channel cable tray: galvanized steel, stainless and aluminum, width 50–600 mm
View product →
Seismic Support Bracket
Seismic bracing for cable trays and MEP, hot-dip galvanized, GB 50981 compliant. Design su
View product →